Building the new workshop

email: [email protected]
Call or text: 07811 956 776

I built the new workshop myself and it took around 6 months. During that time I carried on my bookbinding work in a smaller space, within the house. Here are just a few pictures to show the progress of the project.



First the old workshop had to be demolished. It was becoming too cramped.


CC449F88-D943-446B-BF0E-E8A213E34F43_1_105_c

The foundations of the new building are supported on steel pillars.


A2010AE8-3E80-411B-9147-8F59D84D0351_1_201_a


The walls are going up.


FDB10E62-5452-40A2-A580-A4CFE7689903_1_105_c


And now the trusses, to support the roof and create a loft space..


9D289DA3-8FC0-4DED-9E9C-50B363261736_1_201_a


The finished building. I didn't want to harm the trees, so I built around them. The workshop is clad with cedar to prevent damage from weather and insects.


D3767344-5025-4C12-8181-59950E3567EC_1_201_a


The inside is very spacious.


93360C52-9B17-4FE3-984D-D843C1BE2743_1_201_a00CF4037-2C0A-42A5-9A5D-2A07D87FC42A_1_201_a[email protected]